Which one of the following is NOT a valid reason to utilize organizational process assets as a part of the quantitative risk analysis process?

You are the project manager of the GHG project. You are preparing for the quantitative risk
analysis process. You are using organizational process assets to help you complete the
quantitative risk analysis process. Which one of the following is NOT a valid reason to utilize

organizational process assets as a part of the quantitative risk analysis process?

You are the project manager of the GHG project. You are preparing for the quantitative risk
analysis process. You are using organizational process assets to help you complete the
quantitative risk analysis process. Which one of the following is NOT a valid reason to utilize

organizational process assets as a part of the quantitative risk analysis process?

A.
You will use organizational process assets for risk databases that may be available
from industry sources.

B.
You will use organizational process assets for studies of similar projects by risk
specialists.

C.
You will use organizational process assets to determine costs of all risks events
within thecurrent project.

D.
You will use organizational process assets for information from prior similar projects



Leave a Reply 0

Your email address will not be published. Required fields are marked *