You and your project team are just starting the risk identification activities for a project that
is scheduled to last for 18 months. Your project team has already identified a long list of
risks that need to be analyzed. How often should you and the project team do risk
identification?
A.
Several times until the project moves into execution
B.
It depends on how many risks are initially identified.
C.
At least once per month
D.
Identify risks is an iterative process.