What is the only output of the quantitative risk analysis process?

You are the project manager of the NKQ project for your organization. You have completed
the quantitative risk analysis process for this portion of the project. What is the only output
of the quantitative risk analysis process?

You are the project manager of the NKQ project for your organization. You have completed
the quantitative risk analysis process for this portion of the project. What is the only output
of the quantitative risk analysis process?

A.
Risk register updates

B.
Risk response

C.
Risk contingency reserve

D.
Probability of reaching project objectives