Positive risk events, such as these within the NHJ Project are also known as what?

Thomas is the project manager of the NHJ Project for his company. He has identified
several positive risk events within his project and he thinks these events can save the
project time and money. Positive risk events, such as these within the NHJ Project are also
known as what?

Thomas is the project manager of the NHJ Project for his company. He has identified
several positive risk events within his project and he thinks these events can save the
project time and money. Positive risk events, such as these within the NHJ Project are also
known as what?

A.
Benefits

B.
Ancillary constituent components

C.
Opportunities

D.
Contingency risks



Leave a Reply 0

Your email address will not be published. Required fields are marked *