You are the project manager for your organization. You are working with your key
stakeholders in the qualitative risk analysis process. You understand that there is certain
bias towards the risk events in the project that you need to address, manage, and ideally
reduce. What solution does the PMBOK recommend to reduce the influence of bias during
qualitative risk analysis?
A.
Establish the definitions of the levels of probability and impact
B.
Isolate the stakeholders by project phases to determine their risk bias
C.
Involve all stakeholders to vote on the probability and impact of the risk events
D.
Provideiterations of risk analysis for true reflection of a risk probability and impact