Mark is the project manager of the BFL project for his organization. He and the project team
are creating a probability and impact matrix using RAG rating. There is some confusion and
disagreement among the project team as to how a certain risk is important and priority for
attention should be managed. Where can Mark determine the priority of a risk given its
probability and impact?
A.
Look-up table
B.
Risk management plan
C.
Project sponsor
D.
Risk response plan