A high-profile, high-priority project within your organization is being created. Management
wants you to pay special attention to the project risks and do all that you can to ensure that
all of the risks are identified early in the project. Management has to ensure that this project
succeeds. Management’s risk aversion in this project is associated with what term?
A.
Quantitativerisk analysis
B.
Risk mitigation
C.
Risk conscience
D.
Utility function