Which risk response will likely cause a project to use the procurement processes?

You work as a project manager for BlueWell Inc. You are working with your team members
on the risk responses in the project. Which risk response will likely cause a project to use

the procurement processes?

You work as a project manager for BlueWell Inc. You are working with your team members
on the risk responses in the project. Which risk response will likely cause a project to use

the procurement processes?

A.
Acceptance

B.
Mitigation

C.
Exploiting

D.
Sharing



Leave a Reply 0

Your email address will not be published. Required fields are marked *