Fred is the project manager of the CPS project. He is working with his project team to
prioritize the identified risks within the CPS project. He and the team are prioritizing risks for
further analysis or action by assessing and combining the risks probability of occurrence
and impact. What process is Fred completing?
A.
Perform quantitative analysis
B.
Perform qualitative analysis
C.
Risk identification
D.
Risk Breakdown Structure creation