What individual should respond to the risk with the preplanned risk response?

Diane is the project manager of the HGF Project. A risk that has been identified and
analyzed in the project planning processes is now coming into fruition. What individual
should respond to the risk with the preplanned risk response?

Diane is the project manager of the HGF Project. A risk that has been identified and
analyzed in the project planning processes is now coming into fruition. What individual
should respond to the risk with the preplanned risk response?

A.
Diane

B.
Risk owner

C.
Subject matter expert

D.
Project sponsor



Leave a Reply 0

Your email address will not be published. Required fields are marked *