You are the project manager for a construction project. The project involves casting of a
column in a very narrow space. Because of lack of space, casting it is highly dangerous.
High technical skill will be required for casting that column. You decide to hire a local expert
team for casting that column. Which of the following types of risk response are you
following?
A.
Mitigation
B.
Avoidance
C.
Transference
D.
Acceptance