You and your project team have identified the project risks and now are analyzing the
probability and impact of the risks. What type of analysis of the risks provides a quick and
high-level review of each identified risk event?
A.
A risk probability-impact matrix
B.
Quantitative risk analysis
C.
Seven risk responses
D.
Qualitative risk analysis