Tom is the project manager for his organization. In his project he has recently finished the
risk response planning. He tells his manager that he will now need to update the cost and
schedule baselines. Why would the risk response planning cause Tom the need to update
the cost and schedule baselines?
A.
Baselines should not be updated, but refined through versions.
B.
New or omitted work as part of a risk response can cause changes to the cost
and/or schedule baseline.
C.
Risk responses protect the time and investment of the project.
D.
Risk responses may take time and money to implement.