During which of the following processes, probability and impact matrix is prepared?
A.
Plan Risk Responses
B.
Perform Quantitative Risk Analysis
C.
Perform Qualitative Risk Analysis
D.
Monitoring and Control Risks
During which of the following processes, probability and impact matrix is prepared?
During which of the following processes, probability and impact matrix is prepared?
A.
Plan Risk Responses
B.
Perform Quantitative Risk Analysis
C.
Perform Qualitative Risk Analysis
D.
Monitoring and Control Risks