You are working as a project manager in your organization. You are nearing the final stages of project execution and looking towards the final risk monitoring and controlling activities. For your project archives, which one of the following is an output of risk monitoring and control?
A.
Quantitative risk analysis
B.
Requested changes
C.
Risk audits
D.
Qualitative risk analysis
Explanation:
Of all the choices presented, only requested changes is an output of the monitor and control risks process. You might also have risk register updates, recommended corrective and preventive actions, organizational process assets, and updates to the project management plan.
Answer options D and A are incorrect. These are the plan risk management processes.
Answer option C is incorrect. Risk audit is a risk monitoring and control technique.
Reference: Chapter 11. A Guide to the Project Management Body of Knowledge, (PMBOK Guide), Fourth Edition, ISBN:9781933890517, Section 11.6.3.