You are the project manager of the NHH project for your company. You have completed the first round of risk management planning and have created four outputs of the risk response planning process. Which one of the following is NOT an output of the risk response planning?
A.
Project document updates
B.
Risk-related contract decisions
C.
Risk register updates
D.
Organizational process assets updates
Explanation:
Updates to the organizational process assets are not one of the four outputs of the risk response planning.
The outputs of the risk response planning process are:
Risk Register Updates: The risk register is written in detail so that it can be related to the priority ranking and the planned response.
Risk Related Contract Decisions: Risk related contract decisions are the decisions to transmit risk, such as services, agreements for insurance, and other items as required. It provides a means for sharing risks. Project Management Plan Updates: Some of the elements of the project management plan updates are:
Schedule management plan
Cost management plan
Quality management plan
Procurement management plan
Human resource management plan
Work breakdown structure
Schedule baseline
Cost performance baseline
Project Document Updates: Some of the project documents that can be updated includes:
Assumption log updatesTechnical documentation updates
Reference: "Project Management Body of Knowledge (PMBOK Guide), Fourth Edition"