You are working with Anna on your project to determine and map the probability distributions of risk within the project. You have indicated that you will use the uniform distribution method for a portion of the project. Which part of your project is most likely to have a uniform risk distribution?
A.
Late completion stages of a project
B.
Project initiating
C.
Project phases that deal with "cutover" technologies
D.
Early concept stage of design
Explanation:
The early concept stage of a design is a typical phase where the risk is uniform.
Answer option B is incorrect. Project initiating is a project management process group, and not a phase of the project.
Answer option A is incorrect. Late stages of a project may have wild distributions of risks depending on the work that is being completed in the project.
Answer option C is incorrect. "Cutover" technologies, such as moving from one computer operating system to another, is a triangular risk distribution.
Reference: "Project Management Body of Knowledge (PMBOK Guide), Fourth Edition"