which one?

During qualitative risk analysis you want to define the risk urgency assessment. All of the following are indicators of risk priority except for which one?

During qualitative risk analysis you want to define the risk urgency assessment. All of the following are indicators of risk priority except for which one?

A.
Warning signs

B.
Symptoms

C.
Risk rating

D.
Cost of the project

Explanation:

The cost of the project is not an indicator of risk urgency. The affect of the risk on the overall cost of the project may be considered, but it is not the best answer.

Answer option B is incorrect. Symptoms are an indicator of the risk urgency.

Answer option A is incorrect. Warning signs are an indicator of the risk urgency.

Answer option C is incorrect. The risk rating can be an indicator of the risk urgency.

Reference: "Project Management Body of Knowledge (PMBOK Guide), Fourth Edition"



Leave a Reply 0

Your email address will not be published. Required fields are marked *