You work as the project manager for Bluewell Inc. Your project has several risks that will affect several stakeholder requirements. Which project management plan will define who will be available to share information on the project risks?
A.
Communications Management Plan
B.
Resource Management Plan
C.
Risk Management Plan
D.
Stakeholder management strategy
Explanation:
The Communications Management Plan defines, in regard to risk management, who will be available to share information on risks and responses throughout the project.
The Communications Management Plan aims to define the communication necessities for the project and how the information will be circulated. The Communications Management Plan sets the communication structure for the project. This structure provides guidance for communication throughout the project’s life and is updated as communication needs change. The Communication Managements Plan identifies and defines the roles of persons concerned with the project. It includes a matrix known as the communication matrix to map the communication requirements of the project.
Answer option D is incorrect. The stakeholder management strategy does not address risk communications.
Answer option C is incorrect. The Risk Management Plan defines risk identification, analysis, response, and monitoring.
Answer option B is incorrect. The Resource Management Plan does not define risk communications.
Reference: "Project Management Body of Knowledge (PMBOK Guide), Fourth Edition"