Which of the following are included in the risk register?

You are the project manager for TTP project. You are in the Identify Risks process. You have to create the risk register. Which of the following are included in the risk register? Each correct answer represents a complete solution. Choose two.

You are the project manager for TTP project. You are in the Identify Risks process. You have to create the risk register. Which of the following are included in the risk register? Each correct answer represents a complete solution. Choose two.

A.
List of mitigation techniques

B.
List of potential responses

C.
List of key stakeholders

D.
List of identified risks

Explanation:

Risk register is a document that contains the results of the qualitative risk analysis, quantitative risk analysis, and risk response planning.
Description, category, cause, probability of occurring, impact on objectives, proposed responses, owner, and the current status of all identified risks are put in the risk register. Risk register primarily contains the following:

List of identified risks: A reasonable description of the identified risks is noted in the risk register. The description includes event, cause, effect, impact related to the risks identified. In addition to the list of identified risks, the root causes of those risks may appear in the risk register. List of potential responses: Potential responses to a risk may be identified during the Identify Risks process. These responses are useful as inputs to the Plan Risk Responses process.

Answer options A and C are incorrect. List of mitigation techniques and key stakeholders are not parts of the risk register.

Reference: A Guide to the Project Management Body of Knowledge, (PMBOK Guide), Fourth Edition, ISBN:9781933890517, Section 11.2.3.



Leave a Reply 0

Your email address will not be published. Required fields are marked *