Which of the following statements best describes the level of detail Lisa should include with the risk responses she has created?

Lisa is the project manager of the SQL project for her company. She has completed the risk response planning with her project team and is now ready to update the risk register to reflect the risk response. Which of the following statements best describes the level of detail Lisa should include with the risk responses she has created?

Lisa is the project manager of the SQL project for her company. She has completed the risk response planning with her project team and is now ready to update the risk register to reflect the risk response. Which of the following statements best describes the level of detail Lisa should include with the risk responses she has created?

A.
The level of detail should correspond with the priority ranking.

B.
The level of detail is set of project risk governance.

C.
The level of detail must define exactly the risk response for each identified risk.

D.
The level of detail is set by historical information.

Explanation:

The risk register is not a detailed definition of the risk response, but the level of detail should correspond with the priority ranking for the risk.
In other words, the higher the risk priority the more detail the risk will need.

Answer option B is incorrect. This is not a valid statement about the level detail for the risk response.

Answer option D is incorrect. Risk detail, planning, and response could be based on historical information, but this is not the best choice.

Answer option C is incorrect. Not all risks should have a documented risk response as some risks have low impact and low probability.

Reference: "Project Management Body of Knowledge (PMBOK Guide), Fourth Edition"



Leave a Reply 0

Your email address will not be published. Required fields are marked *