The Project Risk Management knowledge area focuses on which of the following processes? Each correct answer represents a complete solution. Choose all that apply.

The Project Risk Management knowledge area focuses on which of the following processes? Each correct answer represents a complete solution. Choose all that apply.

A.
Potential Risk Monitoring

B.
Risk Monitoring and Control

C.
Quantitative Risk Analysis

D.
Risk Management Planning

Explanation:

The Project Risk Management knowledge area focuses on the following processes:
Risk Management Planning
Risk Identification
Qualitative Risk Analysis
Quantitative Risk Analysis
Risk Response Planning
Risk Monitoring and Control

Answer option A is incorrect. There is no such process in the Project Risk Management knowledge area.

Reference: "A Guide to the Project Management Body of Knowledge, (PMBOK Guide)"