You are the project manager of the GGG project. You have completed the risk identification process for the initial phases of your project. As you begin to document the risk events in the risk register what additional information can you associate with the identified risk events?
A.
Risk schedule
B.
Risk cost
C.
Risk potential responses
D.
Risk owner
Explanation:
When risks are entered into the risk register you may also identify potential risk responses for risks within the project.
Answer option D is incorrect. Risk owners are identified during the risk response planning.
Answer option A is incorrect. The risk schedule is not a component of the risk register, though you may document when the risk event may happen as a part of the risk attributes.
Answer option B is incorrect. Risk costs define the cost of the impact, which is a part of qualitative risk analysis.
Reference: "Project Management Body of Knowledge (PMBOK Guide), Fourth Edition"