You are the project manager of QSL project for your organization. You are working with your project team and several key stakeholders to create a diagram that shows how various elements of a system interrelate and the mechanism of causation within the system. What diagramming technique are you using as a part of the risk identification process?
A.
System or process flowcharts
B.
Predecessor and successor diagramming
C.
Influence diagrams
D.
Cause and effect diagrams
Explanation:
In this example you are using a system or process flowchart. These can help identify risks within the process flow, such as bottlenecks or redundancy.
Answer option D is incorrect. A cause and effect diagram, also known as an Ishikawa or fishbone diagram, can reveal causal ors to the effect to be solved.
Answer option C is incorrect. An influence diagram shows causal influences, time ordering of events and relationships among variables and outcomes.
Answer option B is incorrect. Predecessor and successor diagramming is not a valid risk identification term.
Reference: "Project Management Body of Knowledge (PMBOK Guide), Fourth Edition"