Which one of the following is NOT a valid reason to utilize organizational process assets as a part of the quantitative risk analysis process?

You are the project manager of the GHG project. You are preparing for the quantitative risk analysis process. You are using organizational process assets to help you complete the quantitative risk analysis process. Which one of the following is NOT a valid reason to utilize organizational process assets as a part of the quantitative risk analysis process?

You are the project manager of the GHG project. You are preparing for the quantitative risk analysis process. You are using organizational process assets to help you complete the quantitative risk analysis process. Which one of the following is NOT a valid reason to utilize organizational process assets as a part of the quantitative risk analysis process?

A.
You will use organizational process assets for studies of similar projects by risk specialists.

B.
You will use organizational process assets for risk databases that may be available from industry sources.

C.
You will use organizational process assets to determine costs of all risks events within the current project.

D.
You will use organizational process assets for information from prior similar projects.

Explanation:

Of all the given choices, this is the most likely answer. Organizational process assets can not really tell the costs of all risks events within the current project because each project is slightly different. While organizational process assets can identify probable risk events and their costs, it is unlikely that organizational process assets can forecast the costs of all risk events within a given project.

Answer option D is incorrect. This is a true statement about organizational process assets, so it is not a valid answer for this question.

Answer option A is incorrect. This is a true statement about organizational process assets, so it is not a valid answer for this question.

Answer option B is incorrect. This is a true statement about organizational process assets, so it is not a valid answer for this question.

Reference: "Project Management Body of Knowledge (PMBOK Guide), Fourth Edition"



Leave a Reply 0

Your email address will not be published. Required fields are marked *