Which one of the following is the only output for the qualitative risk analysis process?

Which one of the following is the only output for the qualitative risk analysis process?

Which one of the following is the only output for the qualitative risk analysis process?

A.
Organizational process assets

B.
Project management plan

C.
Enterprise environmental ors

D.
Risk register updates

Explanation:

Risk register update is the only output of the choices presented for the qualitative risk analysis process. The four inputs for the qualitative risk analysis process are the risk register, risk management plan, project scope statement, and organizational process assets.
The output of perform qualitative risk analysis process is Risk Register Updates. Risk register is updated with the information from perform qualitative risk analysis and the updated risk register is included in the project documents. Updates include the following important elements.
Relative ranking or priority list of project risks
Risks grouped by categories
Causes of risk or project areas requiring particular attention List of risks requiring response in the near-term
List of risks for additional analysis and response
Watchlist of low priority risks
Trends in qualitative risk analysis results
Answer options A, C, and B are incorrect. These are not the valid outputs for the qualitative risk analysis process.
Reference: "Project Management Body of Knowledge (PMBOK Guide), Fourth Edition"