Management wants you to create a visual diagram of what resources will be utilized in the project deliverables. What type of a chart is management asking you to create?
A.
Work breakdown structure
B.
RACI chart
C.
Resource breakdown structure
D.
Roles and responsibility matrix
Explanation:
A resource breakdown structure is a visual diagram depicting the resources that will be used within the project.
Answer option A is incorrect. The work breakdown structure is a visual diagram of the project deliverables the project will create.
Answer option D is incorrect. The roles and responsibility matrix maps roles to the project assignments. Answer option B is incorrect. A RACI chart is a responsibility assignment matrix using the legend of responsible, accountable, consult, and inform.
Reference: Chapter 5. A Guide to the Project Management Body of Knowledge, (PMBOK Guide), Fourth Edition, ISBN.9781933890517, Section 5.3.3.1.
I have the same idea. C