Why is the schedule management plan needed for quantitative risk analysis?

Mary is the project manager for the BLB project. She has instructed the project team to assemble, to review the risks. She has included the schedule management plan as an input for the quantitative risk analysis process. Why is the schedule management plan needed for quantitative risk analysis?

Mary is the project manager for the BLB project. She has instructed the project team to assemble, to review the risks. She has included the schedule management plan as an input for the quantitative risk analysis process. Why is the schedule management plan needed for quantitative risk analysis?

A.
Mary will utilize the schedule controls and the nature of the schedule for the quantitative
analysis of the schedule.

B.
Mary will schedule when the identified risks are likely to happen and affect the project schedule.

C.
Mary will utilize the schedule controls to determine how risks may be allowed to change the project schedule.

D.
Mary will use the schedule management plan to schedule the risk identification meetings throughout the remaining project.

Explanation:

The controls within the schedule management plan can shape how quantitative risk analysis will be performed on the schedule.
Answer option D is incorrect. This is not a valid answer for this happens throughout the project, but it is not scheduled during the quantitative risk analysis process. Answer option B is incorrect. When risks are likely to happen is important, but it is not the best answer for this Answer option C is incorrect. Risks may affect the project schedule, but this is not the best answer for the
Reference: "Project Management Body of Knowledge (PMBOK Guide), Fourth Edition"



Leave a Reply 2

Your email address will not be published. Required fields are marked *


networkmanagers

networkmanagers

I have the same idea. A

Syndi

Syndi

hi networkmanagers,

Any recommendations on what to study for the CAP test?