You are preparing to start the qualitative risk analysis process for your project. You will be relying on some organizational process assets to influence the process. Which one of the following is NOT a probable reason for relying on organizational process assets as an input for qualitative risk analysis?
A.
Information on prior, similar projects
B.
Studies of similar projects by risk specialists
C.
Risk databases that may be available from industry sources
D.
Review of vendor contracts to examine risks in past projects
Explanation:
A review of vendor contracts for risks in past projects is not a valid reason to rely on organizational process assets.
Answer option A is incorrect. Information on prior, similar projects can help analyze risks in the current project.
Answer option B is incorrect. Studies of similar projects by risk specialists can help analyze risks in the current project.
Answer option C is incorrect. Risk databases that may be available from industry sources are a part of organizational process assets.
Reference: "Project Management Body of Knowledge (PMBOK Guide), Fourth Edition"
D