Kelly is the project manager of the BHH project for her organization. She is completing the risk identification process for this portion of her project. Which one of the following is the only thing that the risk identification process will create for Kelly?
A.
Risk register updates
B.
Change requests
C.
Risk register
D.
Project document updates
Explanation:
The risk register is the only output of the risk identification process. Risk register is a document that contains the results of the qualitative risk analysis, quantitative risk analysis, and risk response planning. Description, category, cause, probability of occurring, impact on objectives, proposed responses, owner, and the current status of all identified risks are put in the risk register. Answer option A is incorrect. Risk register updates are not a valid output for the risk identification process. Answer option D is incorrect. Project document updates are not a valid output of the risk identification process.
Answer option B is incorrect. Change requests are not a valid output of the risk identification process. Reference: "Project Management Body of Knowledge (PMBOK Guide), Fourth Edition"
C