What project management plan is most likely to direct the quantitative risk analysis process for a project in a matrix environment?
A.
Staffing management plan
B.
Risk analysis plan
C.
Risk management plan
D.
Human resource management plan
Explanation:
The risk management plan defines how risks will be identified, analyzed, responded to, and then monitored and controlled regardless of the structure of the organization. Answer option D is incorrect. The human resources management plan does define how risks will be analyzed.
Answer option A is incorrect. The staffing management plan does define how risks will be analyzed. Answer option B is incorrect. The risk analysis plan does define how risks will be analyzed. Reference: "Project Management Body of Knowledge (PMBOK Guide), Fourth Edition"
C