A high-profile, high-priority project within your organization is being created. Management wants you to pay special attention to the project risks and do all that you can to ensure that all of the risks are identified early in the project. Management has to ensure that this project succeeds.
Management’s risk aversion in this project is associated with what term?
A.
Utility function
B.
Risk conscience
C.
Quantitativerisk analysis
D.
Risk mitigation