DRAG DROP
You manage a solution deployed in two Azure subscriptions for testing and production. Both subscriptions
have virtual networks named fabVNet.
You plan to add two new virtual machines (VMs) in a new subnet.
You have the following requirements:
Deploy the new VMs to the virtual network in the testing subscription.
Minimize any errors in defining the network changes.
Minimize the work that will be required when the change is made to the
production virtual network.
Which three steps should you perform in sequence? To answer, move the appropriate actions from the list
of actions to the answer area and arrange them in the correct order.
Answer: See the explanation
Explanation:
Box 1: Add a subnet to the network configuration file.
Box 2: Import the network configuration.
Box 3: Deploy the new VMs to the new subnet.
After you’ve configured your network configuration file, use the procedure below to import it into the
Management Portal.
To import a network configuration file:
1. Log on to the Management Portal.
2. In the navigation pane on the bottom left, click New.
3. Click Network Services-> Virtual Network-> Import Configuration.
4. On the Import the network configuration file page, browse to your network configuration file, and
then click the next arrow.
5. Your virtual network is created.Virtual Network Configuration Tasks
URL: http://msdn.microsoft.com/en-us/library/azure/jj156206.aspx
How about: 2-3-6??
Yes that seems correct
I think it should be:
1.-Add a subnet to the network configuration file
2.-Export the network configuration
3.-Import the network configuration