There are three primary baselines in a project. Which one of the following is NOT a baseline that can be captured in Microsoft Project Server?
A.
Schedule
B.
Cost
C.
Quality
D.
Scope
Explanation:
Quality is not a project management baseline. Scope often serves as the quality baseline as it represents all that the project should deliver. Answer option B is incorrect. Cost is one of the three baselines and it can be kept and measured in Microsoft Project Server. Answer option D is incorrect. Scope is a constant baseline; it consists of the project scope statement, work breakdown structure, and the WBS dictionary. Answer option A is incorrect. You can create and maintain a schedule baseline in Microsoft Project Server.