What option must you choose in the Resource Substitution Wizard in order to test the addition of specific resources?

You work as the Project Administrator for company.com Inc. The company uses Microsoft Project Server 2010 to manage the project development process. You need to perform a skill-based scheduling task on the basis of the skill-based resources in your project. You are using the Resource Substitution Wizard to evaluate and swap the actual resources with the defined skill resources. In the Resource Substitution Wizard, you would like the wizard to examine the application of five specific resources in your project to test the allocation of these resources. What option must you choose in the Resource Substitution Wizard in order to test the addition of specific resources?

You work as the Project Administrator for company.com Inc. The company uses Microsoft Project Server 2010 to manage the project development process. You need to perform a skill-based scheduling task on the basis of the skill-based resources in your project. You are using the Resource Substitution Wizard to evaluate and swap the actual resources with the defined skill resources. In the Resource Substitution Wizard, you would like the wizard to examine the application of five specific resources in your project to test the allocation of these resources. What option must you choose in the Resource Substitution Wizard in order to test the addition of specific resources?

A.
When the wizard asks you to choose resources, select the option “In the Selected Projects” and then Next.

B.
When the wizard asks you to choose resources, select the option “Specify Resources” and then Next.

C.
You cannot specify specific resources when using skill-based scheduling.

D.
When the wizard asks you to choose resources, select the option “Specified Below” and choose the specific resources you want to add.

Explanation:
You can choose the resources you want to add to your project by choosing the option “Specific Below” and then picking specific resources. Answer option C is incorrect. You can choose resources when using skills-based scheduling.
Answer option A is incorrect. The option “In the Selected Projects” will only use resources that are currently used in the existing projects you select. Answer option B is incorrect. There is no such option as “Specify Resources” in the Resource Substitution Wizard. What is the Resource Substitution Wizard? The Resource Substitution Wizard is used to perform resource workload analysis and then make decisions about which resources can be used to perform certain scheduled tasks. The enterprise custom field attributes are used by this wizard to make resource matching decisions during the workload analysis phase. It attempts to substitute resources having less workload for overloaded resources within the constraints of enterprise custom field attribute settings.



Leave a Reply 0

Your email address will not be published. Required fields are marked *