Which one of the following is not one of the four areas of change control?

You are the Microsoft Project Server administrator for your company. You have been working with your project managers to develop a change control system for their projects. In the change control system, you want to provide a method to document any changes from the areas of the project the change stems from. There are, in practical project management, four areas of change control that should be managed by each project manager. Which one of the following is not one of the four areas of change control?

You are the Microsoft Project Server administrator for your company. You have been working with your project managers to develop a change control system for their projects. In the change control system, you want to provide a method to document any changes from the areas of the project the change stems from. There are, in practical project management, four areas of change control that should be managed by each project manager. Which one of the following is not one of the four areas of change control?

A.
Scope

B.
Cost

C.
Quality

D.
Procurement

Explanation:
Quality is not a change control area. The four areas of change control that should be documented by your project management change control system are time, cost, scope, and procurement. Answer option D is incorrect. Procurement is one of the four areas of change control. Answer option B is incorrect. Cost is one of the four areas of change control. Answer option A is incorrect. Scope is one of the four areas of change control.



Leave a Reply 0

Your email address will not be published. Required fields are marked *