You work as a Project Manager of the HHQ Project for your company. You are using the timesheets feature of Microsoft Project Server and Project Web Access so that team members can record the hours spent on their project work. This information is compiled and is used for project billing to the customer. You have another project which is a fixed fee contract and you would not need to keep track of hours spent on each task in the project. You want the team members to report their percentage completion of assignments for project scheduling. Which of the following features of Project Server 2010 should be used by the project team?
A.
My assignments
B.
My timesheets
C.
My projects
D.
My tasks
Explanation:
The ‘My tasks’ page allows the members of a project team to send project managers and others the time-oriented information about the percentage of their tasks they have completed. Answer option B is incorrect. The ‘My time sheets’ page allows the project team members to report the amount of time they have spent on a particular assignment without giving the information about the task completion.
Answer option A is incorrect. My assignments is a view that shows what work has been assigned to an individual who is usually a member of the project team. Answer option C is incorrect. This is not a valid view to enter the time percentage completion information.