You are the Microsoft Project Server administrator for your company. Henry, a project manager in your organization, approaches you about a problem. Management has told Henry that his project team is not to work any overtime on a project. Management would like Henry to provide a report that highlights any project team that has worked overtime on a task within a given time period. Henry needs your assistance to create this report. Which report would you recommend to Henry?
A.
Resource Availability Graph
B.
Status Report
C.
The Timesheet Audit Report
D.
Timesheet Classification
Explanation:
The Timesheet Audit Report is a Project Center report that can be used to highlight types of work, including overtime work, within a given time period. Answer option D is incorrect. Timesheet classification is not a report type, but a method to designate the type of work that is being completed on the project. Answer option A is incorrect. The Resource Availability Graph is not a report, but a charting feature in Project Center. Answer option B is incorrect. The Status Report does not include overtime features and is generally not used for management’s view of the project. It is often for the project team to examine the project work to be done in the project.