How can you access the dialog box to edit the site address of a project workspace?

You work as a Project Administrator for Company Inc. You need to configure SharePoint Server for a new site address for your project workspace. How can you access the dialog box to edit the site address of a project workspace?

You work as a Project Administrator for Company Inc. You need to configure SharePoint Server for a new site address for your project workspace. How can you access the dialog box to edit the site address of a project workspace?

A.
Through the Project Workspaces option of the server settings page

B.
Through the Active Directory Enterprise Resource Pool Synchronization option of the server settings page

C.
Through the Project Server database

D.
Through Active Directory

Explanation:
You can change a site address or remove the URL of the SharePoint Site through the Project Workspaces option under the Operational Policies section of the Server Settings page. You should select the project, and then select the Edit Site Address button to configure SharePoint Server for a new site address for the project workspace. Answer option D is incorrect. Site addresses cannot be changed through Active Directory. Answer option B is incorrect. The Active Directory Enterprise Resource Pool Synchronization is used to manage groups, resource options, and schedules, but not to change the site addresses. Answer option C is incorrect. The site address cannot be changed through the related Project Server database. What is a project workspace?
A Project Workspace is a Microsoft SharePoint Teamsite where the Project team can share documents, issues and risks. A project workspace is created for each project schedule. It is used to leverage WSS technology to enhance communication between project team members. Project managers might use the project workspace to list announcements and events, store a project’s documentation, and navigate to the Issues, Risks, and Documents pages for the project. What are the different methods for creating a project workspace? The different methods for creating a project workspace are as follows:
1.Automatically: A new workspace is created automatically during a publish operation of an activity plan or proposal in PWA.
2.Semi-Automatically: The project owner is given the option to link the project workspace to an existing project workspace during a publish operation of an enterprise project schedule. This is commonly used for master/child project relationships. The project owners can also update the URL of the new project workspace.
3.Manually: The project owner can manually create project workspaces in Project Server. This option allows a project owner to choose whether to create a workspace at the time of a publish operation of an activity plan or proposal in PWA.



Leave a Reply 0

Your email address will not be published. Required fields are marked *