Which of the following cubes should you use if you want to examine the risk-related information such as trigger tasks, risk costs, risk owners?

You are the Microsoft Project Server administrator for Company Inc. You need to determine which cube would be the most appropriate for your project. Which of the following cubes should you use if you want to examine the risk-related information such as trigger tasks, risk costs, risk owners?

You are the Microsoft Project Server administrator for Company Inc. You need to determine which cube would be the most appropriate for your project. Which of the following cubes should you use if you want to examine the risk-related information such as trigger tasks, risk costs, risk owners?

A.
Deliverables cube

B.
Issues cube

C.
Risks cube

D.
EPM Timesheet

Explanation:
The Risks cube allows the user to view all the risk-related information in his project such as risks, trigger tasks, exposure, costs, owners, affected tasks, and more. Answer option B is incorrect. The Issues cube provides the information related to the issue names, status, priority, owners, and more. Answer option A is incorrect. The Deliverables cube provides the information such as deliverable names, projects, dates, and more. Answer option D is incorrect. The EPM Timesheet cube contains the information including the data about projects, resources, tasks, time, fiscal time, resource capacity, and more.



Leave a Reply 0

Your email address will not be published. Required fields are marked *