Which of the following steps will you take to configure this in Microsoft Project Server while using a program?

You work as a Program Manager for Company Inc. You are using Microsoft Project Server as the project management information system for all constituent projects. Some of the projects in this program will take place in different countries. The project managers of these projects have notified you that they will need to reserve certain dates for holidays celebrated in their country that may not be appropriate for other countries. Which of the following steps will you take to configure this in Microsoft Project Server while using a program?

You work as a Program Manager for Company Inc. You are using Microsoft Project Server as the project management information system for all constituent projects. Some of the projects in this program will take place in different countries. The project managers of these projects have notified you that they will need to reserve certain dates for holidays celebrated in their country that may not be appropriate for other countries. Which of the following steps will you take to configure this in Microsoft Project Server while using a program?

A.
The project managers will need to configure Microsoft Project Professional to use the local calendar for lookups rather than the enterprise calendar for scheduling.

B.
This is not a problem, as all projects always use their own local calendar through their Microsoft Project Professional version.

C.
While using a program, all projects within the program must use the same enterprise calendar.

D.
The Microsoft Project Server will need to be configured through Server Settings to allow local base calendars.

Explanation:
The “Additional Server Settings” option in Server Settings > Operational policies can allow projects within the program to use their local base calendar rather than the enterprise calendar. Answer option C is incorrect. Projects within a program can still use their own calendar rather than the enterprise calendar. Answer option B is incorrect. The calendars of the local Microsoft Project Professional do not always use their local calendar. This can be set at the server level, not the local level.
Answer option A is incorrect. The Microsoft Project Server administrator will need to set this feature at the server, not the local instance of Microsoft Project Professional.



Leave a Reply 0

Your email address will not be published. Required fields are marked *