While modifying a project view, you must choose from three table types for the view you are modifying. Which of the following is NOT a Project View table type that you can choose from for modifying a Project View?
A.
Task
B.
Schedule
C.
Resource
D.
Assignment
Explanation:
When you modify a Project View, you do not get to choose a schedule table. You must choose from task, resource, or assignment table. Answer option A is incorrect. The task table is one of the three choices you have when modifying a Project View. The task table displays task information about the project.
Answer option C is incorrect. The resource table includes all available project resources, related information, and their manager contact information if included. This is one of the three tables you must choose from.
Answer option D is incorrect. The assignment table is one of the three tables that you can choose from when modifying a project view. The assignment table defines assignments, assignment owner, and status.