You work as a Project Manager at ABC.com. You are managing a project using Project Server 2010. You have been instructed to create a Project Server resource for the purpose of tracking the number of bricks used in a new ABC.com housing development. Which of the following actions should you take?
A.
You should create a cost resource.
B.
You should create a material resource.
C.
You should create a people resource.
D.
You should create an equipment resource.
E.
You should create a generic resource.