Which of the following actions should you take?

You work as the network administrator at ABC.com. Your responsibilities include maintaining the Project Server 2010 environment. You have created an Enterprise Project Type (EPT) for Marketing projects. There are currently six different projects in progress based on the Marketing EPT. After modifying the workflow on the Marketing EPT, you want to make sure that the six existing projects make use of the new workflow association. Which of the following actions should you take?

You work as the network administrator at ABC.com. Your responsibilities include maintaining the Project Server 2010 environment. You have created an Enterprise Project Type (EPT) for Marketing projects. There are currently six different projects in progress based on the Marketing EPT. After modifying the workflow on the Marketing EPT, you want to make sure that the six existing projects make use of the new workflow association. Which of the following actions should you take?

A.
You should publish new projects using the Marketing EPT.

B.
You should open each project and restart the workflow associations.

C.
You should rename the EPT then associate the projects with it.

D.
You should configure a new workflow stage for each project.



Leave a Reply 0

Your email address will not be published. Required fields are marked *