You work as a Project Manager at ABC.com. You are using the Project Server 2010 environment to manage a project. The project is spread over three regions named Region1, Region2 and Region3. Some project resources work in more than one region. You need to be able to associate project resources with their respective regions. You plan to link a custom field to a lookup table. You configure a multi-value lookup table that lists Region1, Region2 and Region3. Your next step is to create a custom field that should be mapped to the lookup table. Which of the following actions should you take?
A.
You should consider creating a custom user field.
B.
You should consider creating a custom resource field.
C.
You should consider creating a custom project field.
D.
You should consider creating a custom workflow field.