You are the Microsoft Project Server administrator for your company. You have been working with
your project managers to develop a change control system for their projects. In the change control
system, you want to provide a method to document any changes from the areas of the project the
change stems from. There are, in practical project management, four areas of change control that
should be managed by each project manager. Which one of the following is not one of the four areas
of change control?
A.
Scope
B.
Cost
C.
Quality
D.
Procurement
Explanation:
Quality is not a change control area. The four areas of change control that should be documented by
your project management change control
system are time, cost, scope, and procurement.
Answer option D is incorrect. Procurement is one of the four areas of change control.
Answer option B is incorrect. Cost is one of the four areas of change control.
Answer option A is incorrect. Scope is one of the four areas of change control.