You are the Microsoft Project Server administrator for Company Inc. You need to determine which
cube would be the most appropriate for your project. Which of the following cubes should you use if
you want to examine the risk-related information such as trigger tasks, risk costs, risk owners?
A.
Deliverables cube
B.
Issues cube
C.
Risks cube
D.
EPM Timesheet
Explanation:
The Risks cube allows the user to view all the risk-related information in his project such as risks,
trigger tasks, exposure, costs, owners, affected tasks, and more.
Answer option B is incorrect. The Issues cube provides the information related to the issue names,
status, priority, owners, and more.Answer option A is incorrect. The Deliverables cube provides the information such as deliverable
names, projects, dates, and more.
Answer option D is incorrect. The EPM Timesheet cube contains the information including the data
about projects, resources, tasks, time, fiscal time, resource capacity, and more.