You work as a Project Administrator for Company Inc. Your current project is going to finish within a
few days. You would like to keep the information of this project as a project template. If you choose
to save the file as a template, you are allowed to clear all of the following project attributes for the
template except for which one of the following?

You work as a Project Administrator for Company Inc. Your current project is going to finish within a
few days. You would like to keep the information of this project as a project template. If you choose
to save the file as a template, you are allowed to clear all of the following project attributes for the
template except for which one of the following?

A.
Resource rates

B.
Resources

C.
Values of all baselines

D.
Actual values

Explanation:
There is no option to clear the resources that have been used in the project that you are saving as a
template. You are allowed to clear the following five values:
1.Values of all baselines
2.Actual values
3.Resource rates
4.Fixed costs
5.The information about the tasks that have been published on Project Server

Answer options C, D, and A are incorrect. You can clear the values of all baselines, actual values, and
resource rates.
What is a template?
A template is a project that is specially designed to be used more than once. A template has an
extension .mpt. A template has special characteristics, one of which is that the template is saved into
a special location reserved for templates. A template is useful for creating consistent and repeated
activities in a project. Therefore, the user need not have to start the project from scratch.