A section of your project contains only a summary task along with four subtasks and a
milestone. You discover that the section is located in the incorrect phase and has the
incorrect Work Breakdown Structure (WBS) numbering. You need to move the section to
another phase of the project. You also need to ensure that the section reflects the correct
WBS numbering. What should you do?
A.
Select the summary task and change the scheduling mode to Manually Scheduled.
B.
Select the entire section and click Move Task.
C.
Drag the summary task.
D.
Modify the start and finish dates of the summary task.