You manage several projects. Each project has shared resources and work distribution. You
need to ensure that you can adjust the workload for specific resources used across multiple
project schedules. What should you do? 
A.
 Enable the Load Summary Resource Assignments option. Then, select the Level 
Resource function on each project.
B.
 Open the individual schedules and use the Visual Reports option. Then, use the 
Resource Usage view to manually modify resource Work.
C.
 Open a blank project and select Insert Subproject for each project schedule. Then, use 
the Level Resource function for selected resources.
D.
 Open the shared Resource Pool for each project schedule. Then, use the Level 
Resources function.